		 Periodic reports to be submitted by coordinator 60 days after end of period ·         progress of work ·         use of resources ·         Financial Statement (Form C)   Final reports to be submitted by coordinator 60 days after end of project ·         publishable summary report, conclusions and socio-economic impact ·         covering wider societal implications and a plan on use and dissemination of results   Commission has 105 days to evaluate and execute the corresponding payment ·         No tacit approval ·         After reception Commission may: ·         Approve ·         Suspend the time limit requesting revision/completion ·         Reject them giving justification, possible termination ·         Suspend the payment 
 |